Advanced Structural Designs

  

ACN 097 789 87    92 Vasey Cres CAMPBELL ACT 2612

Telephone  61612171         Facsimile 61612170

Email   mal@structuraldesigns.com.au

 

 

 
                                                                                                                                               

                                                                                     

 

What are the Pros and Cons associated with using Ultrafloor on a multistorey residential project?

 

Mal first used Ultrafloor in Canberra in around 1992 with Civil and Civic on the Liberal party headquarters in Barton when the company was just starting to venture outside its base in Newcastle.  The company was keenly marketing and we needed a 9 metre clear span for the extension.  Whilst Ultrafloor did not have beams that would do the job at the time to their credit they built the beams from scratch as they could see that there was no competitor that could span this distance.

 

Since that time Ultrafloor has expanded into most states and has carried out a large amount of research on their product.  This research has been both on strength verifications as well as fire and acoustic performance.  Acoustic performance, which had been a problem area in their earlier years in the multistorey residential market is now one of their strengths.

 

They have also expanded their product range to include band beam construction although they are essentially acting as formwork for the bands, which are stressed in most cases. Mal has used Ultrafloor on a number of projects here and in Sydney and has generally been very satisfied with the company’s performance and professionalism.  Three local projects on which they have been used this year (2002) are Ivan Bullum’s development in Watson, Forum in the City and The Phoenix on Northbourne Ave.

 

The Ultrafloor option is always at its most competitive when formwork is expensive but they believe they can compete in any market.  We seriously consider their use in the following circumstances.

 

·        Where there is a large degree of repetition on the project.

·        The building has a rectangular grid.

·        There are not too many balconies (or the balconies rest within the building envelope).

·        There is a necessity to build walls at less than 8m centres that can be used as load bearing walls.

·        Lateral loads can be adequately handled by the service shafts (rarely a problem under 10 stories).

·        Form workers are busy into the future (and therefore prices high).

·        There is a tight building program*.

·        The builder wants to minimise site labour and/or union disputes.

·        Detailing can achieve a tight floor envelope.

 

The last point is the one most often missed as some of the recent developments in Canberra have sat the Ultrafloor beams on top of deep steel transfer beams at ground floor which has resulted in solutions 300mm or more deeper that the equivalent prestressed banded solution.  This is simply lazy detailing as there are alternatives available to minimise the problem. 

 

If you do require 300 of extra basement to ground floor structural depth you have to incur cost for

 

  1. 300mm of additional excavation.
  2. 300mm more height to retaining walls.
  3. Extra strength to retaining walls (additional bending).
  4. Extra height and strength for all columns (additional slenderness).
  5. Extra 4 metres of ramp to basement (and the loss of amenity/land).
  6. Longer stair runs
  7. Additional SW depths (pumping dewatering etc)

 

To give a feel for what this means on a cost per square metre basis 1 to 4 alone (in rippable rock) will amount to around (10.5+3.1+1.4+0.7) = $15.7/m^2, 5 and 6 may bump this up to $20/m^2 and 7 can be large or negligible depending on water table heights.  The extra basement depth can also make it more difficult to comply with natural ventilation requirements which can be a very heavy cost penalty if mechanical ventilation is required.

 

The same also applies to beams spanning between support walls on typical floors.  It is far preferable to have the Ultrafloor beams and the support beams in the same plane.  To get around this problem it is tempting to go for a steel solution with concrete filling but there are a number of fire rating concerns that need to be properly addressed.  It is our view that a number of solutions currently being used in the ACT cannot be justified to fulfil their design fire rating requirements due to poor detailing.

 

The other construction issue that you may not be aware of is the fact that the Ultrafloor shop drawings are not dimensioned. The philosophy here is that they cater for major penetrations such as AC risers but they do not cater for smaller penetrations such as those required for toilet pans.  This can cause quite a few headaches if the plan geometry is complex as Hindmarsh found out on the Forum.  When the beams and FC are all in place and your surveyor goes around and sets out all of the penetrations every time a penetration lines up with a beam you have a problem and need to add an extra beam.  This is not such a problem if all the beams are the same size but is much more of an issue when they are varying in length.   This problem can be minimised by having a penetrations drawing signed off prior to construction but we can’t say we’ve seen that done for quite some time.

 

Another issue to think about is cranage and speed of erection.  Many of the Ritek or reinforced block wall solutions being used have starter bars protruding from the erected wall.  These can cause a problem whenever a beam lines up with a bar and serious thought should be given to drilling and epoxying splice bars on site.  If the walls are free of obstacles you can often speed the process by craning more than one beam at a time.

 

Be careful not to store any FC in wet conditions as it severely weakens the product and concreters have been injured stepping through weakened planks.

 

Cement leaking through holes in the formwork can also be a costly issue to address later so sealing the joints is normally carried out prior to pouring.  Ramset’s ‘Fomo Plus’ is one of a number of products that can be used for this purpose.  The trick is to use just enough if you don’t want to have to come back with a knife and cut off the excess.

 

The Ultrafloor manual suggests handling cantilevered balconies in certain circumstances using conventional formwork but we believe it is more cost effective to use alternative means and have come up with a number of standard details that eliminate the need for conventional formwork. 

 

Basically you need to do everything possible to avoid mixing Ultrafloor with conventional formwork as the formwork price per m2 will double or triple and the clear workspace under can be lost to scaffolding and form props.  This point seem to have been lost on a number of designers in recent times with any economies or benefits being swamped by the inefficiencies involved in mixing trades.

 

Some thought also needs to go into how steel columns are supported on the top floor as far too often riggers are tearing their hair out trying to support columns on 50mm concrete slabs and in extreme cases being told to scabble out a set down for the base plate.  This issue should be addressed on the shop drawings with thicker slabs provided in appropriate areas.

 

In brief

 

The benefits are

 

  • Speed of construction*
  • Minimised site labour – union disputes
  • Cost (in the right market)
  • Less material wastage on site

 

The drawbacks are

 

  • Monopoly supplier (although notoriously reliable)**
  • Unattractive soffit (if exposed)
  • No dimensions on shop drawings
  • Complex to place if support geometry is not regular (need to cut all of the infill panels and all beams are a different size).
  • Fixing steel columns to thin topping is can cause headaches.

 

* This is perhaps more true on paper than it is in real life as a well designed stressed deck using one of the bigger formworking companies can have a floor cycle of less than a week on a 500-600m2 deck which is very hard to beat.

 

**It is perhaps not fair to say they have a monopoly as Rescrete also supply a somewhat different precast decking system but once you’ve signed up if they don’t perform you don’t have many options.

 

Ultra-floor generally quote a price for design and installation of the planks and Hardiform infill and provide shop drawings of beam layouts out of their Sydney Office after a fixed price is agreed to.  Shop drawings take a minimum of two weeks to produce and they are happy to do deals well into the future if your project has a long lead time.  ASD can produce the shop drawings if you prefer, as can one or two other local consultants.  In this case we are paid $2.50/m2 by Ultra-Floor and the cost to the developer/Builder is unchanged. 

 

Costs per square metre start at around $60 (March 2002) for their smaller beams but this does not include the mesh or concrete topping. 

 

If you need to know more about how it’s done or need a proposal put together by an experienced structural engineer in Canberra or the surrounding region call Mal Wilson from Advanced Structural Designs on Ph 61612171.

 

Home  FAQ