Advanced Structural
Designs ACN 097 789 87
92 Vasey Cres CAMPBELL ACT 2612 Telephone
61612171
Facsimile 61612170 Email mal@structuraldesigns.com.au

Blistering or Efflorescence on the Concrete Surface
During the Power Trowelling Operation

Background
Concreters generally screed and bull float the concrete and wait for the
bleed water to dissipate before they attempt to power trowel the surface of the
concrete. In normal conditions this
often results in the power trowelling commences as soon as the concrete is
capable of supporting the machine.
In hot, dry or windy weather when evaporation rates are above 1.0 litre
per m^2 per hour it is often difficult to see the bleed water as it evaporates
as quickly as it arrives and it is easy to misread the correct time to finish
the surface. The situation can be
deceptive, as the rapidly drying surface is normally hard enough to support the
power trowel machine (i.e. helicopter) well before all of the bleed water has
reached the surface.
When concreting in hot weather it is extremely important to commence
finishing the concrete at the correct time.
This is because commencing the finishing too early seals the surface of
the concrete before all of the bleed water has risen to the surface. This situation often results in small
blisters of concrete around 20 to 30 mm in size and 1 mm deep (sometimes
referred to as laitance) peeling off during the power trowelling operation. In some cases you will see larger delaminations
but the depth is always around 1 to 3 mm.
Another problem can be the discolouration of the surface of coloured
concrete as the bleed water brings deposits of calcium carbonate and other
salts to the surface.
Using Aliphatic Alcohol
In circumstances where evaporation rates are high and pouring must
proceed we recommend the use of aliphatic alcohol to control the evaporation of
bleed water. The alcohol is generally
applied after the screeding and bull floating operations. When the alcohol is
applied the bleed water can be seen to build up under the surface of the
aliphatic alcohol. The primary reason for its use is to prevent plastic
shrinkage from occurring but it can also help with the finishing of the
concrete by preventing the surface becoming too dry.
After the bleed water appears to have dissipated, the surface of the
concrete should be poked with a finger to see if there is more bleed water just
below the surface. This water may be as
far as 5mm or more below the surface.
If more bleed water is present, this normally indicates that the
aliphatic alcohol has evaporated or runoff a sloping pavement and more needs to
be applied. If there is no bleed water
beneath the surface it is generally a sign that power trowelling may commence.
Other options for controlling evaporation such as fog sprays, wind
breaks and shading should also be considered where they can be achieved cost
effectively.
Early Start
If the concreter has started the power trowel operation too early it is
sometimes possible to flatten the angle of the blades to help release the bleed
water and to steepen the angle on subsequent passes where a burnished surface
is required in the specification. It is
far preferable of course is not to start power trowelling to early.
Mix Design
High amount of cement paste, fly ash, oxide colouring, fine sand or even
entrained air in the mix can contribute to the rapid sealing of the surface
during the power trowelling operation and it may be possible to reduce one or
more of these by adjusting the mix design.
The use of a dry shake to colour the concrete can be particularly
troublesome, as it will tend to seal the surface and soak bleed water at the
same time.
If the mix is using a super-plasticizer the problem can often be severe
as the bleed water has a tendency to arrive late and fast. Whenever a super-plasticizer is used the
concreter needs to be involved in the decision and informed as to the likely
behaviour of the mix as he may need to wait longer and have more finishers available.
The Weather
When forecasts indicate evaporation losses higher than about 1.2 l/m^/hr
it is generally preferable to postpone the pour until the weather is more
conducive to attaining a high quality finish.
Below is a chart (based on ACI 305) that you can use to estimate likely
evaporation rates for any given relative humidity, air temperature concrete
temperature and wind speed.
Seriously consider wetting down the surrounding area where dust is a
problem as dust landing on the slab can rapidly soak up any bleed water and
contribute to the problem. Also ensure
that the sub-grade beneath the slab (if pouring slab on ground) has been soaked
but has no free water on the surface.
This will provide more bleed water to the surface and help with the finishing.
In a
With the high moisture retention rates being exhibited by some powered
oxides (they are not all the same), there is even an argument for limiting
pouring to days where evaporation rates are less than 1 l/m^2/hr when pouring
coloured concrete. Any such decision
would of course need to fit within programming constraints.
All of the above information relates to blistering in hot weather which
is when the problem is normally at its worst in
The above is but a brief summary of what is a very complex topic, so if
you have any further queries or need an on site appraisal in Canberra ACT by an
experienced structural engineer please do not hesitate to call Mal Wilson from
Advanced Structural Designs Ph 02 61612171.