Advanced Structural Designs

  

ACN 097 789 87   92 Vasey Cres CAMPBELL ACT 2612

Telephone  61612171         Facsimile 61612170

Email   mal@structuraldesigns.com.au

 

 

 
                                                                                                                                               

                                                                                     

 

What was so innovative about Impulse’s Big Space hanger at the Canberra Airport?

 

The Structure

The structure’s clear span is about 82 metres and you can park a 22m high Boeing 717 in it.  It is predominantly constructed of square hollow sections and consists of trussed arches supported on trussed cantilevered support frames with a knee brace added to transfer some moments out of the arch.

 

The major innovation in the structure was the use of bundled prestressing wires in the bottom chord of the trussed arches and in the outer chords of the support trusses.  These prestressing wires were stressed to impart compression into the truss chords effectively cancelling out the dead load deflections.  While the columns where stressed before erection, the arch bottom chords where stressed in two stages.  Both columns and the bottom chords where grout filled (columns from the base up) which both adds to their compressive strength and increases their fire performance.

 

The major benefit of this approach was to save weight in the structure since steel SHS’s used have an ultimate strength of 450MPa compared with 1280MPa for the stressing wires.  This benefit along with the ability to control the initial compressive stress in the truss top chord and the support outer chord led to a claimed overall weight saving on the project of around 40%.

 

The approach was not without certain penalties as the bottom chord was very slender and required a great deal of additional lateral bracing before pairs of trusses could be lifted into place.  A special lifting jig was also required as the large spans could only be lifted at the extremities and the tendency for the paired trusses to flip over was quite pronounced.

 

The final product looks slender and attractive but on the day of inspection the trusses could be seen to move up and down 20 mm under a moderate breeze.  In normal circumstances this would be expected but given the gantry cranes hanging overhead we could not help but wonder whether this might become a serviceability issue.

 

The Hardstand

The hardstand was a design and construct job by Austress Freyssinet.  Since the tensile capacity of the concrete is generally the limiting factor in the strength of the pavement it is not that surprising that stressing the slab was found to be a viable solution.  We were surprised to hear that a major saving was reduction in base coarse thickness (of 400mm?) as base coarse under a rigid pavement is normally only deep enough to control pumping etc (say 200).  In any case the potential creep and shrinkage of such a pavement is considerable so the structure was isolated from the pavement and all services penetrating the pavement were fitted with compressible collars.

 

The construction was overseen by Construction Controls Alan Carey and completed in around 8 months and cost around $12million.

 

As an interesting footnote the new larger hanger being constructed on the RAAF side of theCanberra International Airport is STRARCH design due for erection later this year.  Big space did bid on this project as well but were too expensive.  If you need an independent engineering assessment of the various options for aircraft hangers contact Mal Wilson from Advanced Structural Designs on 02 61612171.

 

Home    FAQ's